Ethan Howland reported for Utility Dive on September 24 that the U.S. Department of Energy selected 31 grid projects for $1.9 billion in grants, an award package expected to unlock 23 gigawatts of additional transmission capacity. Jeff St. John at Canary Media covered the same announcement and put the geography and the matching money on the table: 31 projects across 26 states, with $3.35 billion committed by the utilities and agencies themselves, for a combined $5.25 billion.

The program is called SPARK, which unpacks to Speed to Power through Accelerated Reconductoring and other Key Advanced Transmission Technology Upgrades. It is funded through the Infrastructure Investment and Jobs Act. Strip the acronym and here is the actual job: crews will reconductor or rebuild more than 1,500 miles of transmission line that already exists, and hang grid enhancing technologies on nearly 21,000 miles more.

The list of recipients reads like a roll call of the companies that employ line crews. American Electric Power. CenterPoint Energy. Duke Energy. Eversource Energy. Rocky Mountain Power. PPL Electric Utilities. Alabama Power. Kit Carson Electric Cooperative, plus four public power utilities and rural cooperatives in Arizona, New Mexico and North Carolina. The two largest projects are state led and cross seams: a $1.2 billion Colorado Energy Office project and the $832 million Three Corners Connection in Oklahoma, each carrying a $250 million federal share, both aimed at moving more power between the eastern and western halves of the country.

For a sense of what one of these looks like on the ground, take Pennsylvania. Marin Holt at mgrid reported that PPL Electric Utilities was selected for up to $71.5 million for the Montour Grid Resilience and Advanced Reconductoring Project, which rebuilds roughly 29.3 miles of an existing 230 kilovolt corridor. PPL's own announcement that day adds the hardware: advanced conductors, both ACSS and ACCC types, and a dual optical ground wire carrying distributed acoustic sensing, across the Susquehanna Valley, the greater Lehigh Valley and northeast Pennsylvania. PPL Electric serves about 1.5 million homes and businesses.

"These selected SPARK projects put advanced transmission technologies to work, modernizing critical infrastructure, maximizing the capacity of existing lines, and unlocking more than 20 GW of additional grid capacity," said Catherine Jereza, assistant secretary for the DOE Office of Electricity, in the Utility Dive account.

Why it counts

Reconductoring is the least glamorous idea in the power business and one of the most useful. You keep the towers and the right of way you already own, and you replace the wire hanging on them with a better wire. An advanced conductor runs a composite or carbon fiber core instead of steel, sags less when it heats up, and carries 50 to 110 percent more current on the same structures.

None of that happens by itself. Somebody pulls the old conductor down and the new conductor up, tower by tower, in traffic and weather, on a line that has to be back in service on schedule. That is a line crew, and around it a whole payroll: operators running pullers and tensioners, riggers, groundmen, flaggers, engineers sizing the new sag and tension, and fiber technicians splicing the optical ground wire that turns the line into a sensor.

A lineworker in a yellow hard hat works on crossarm insulators from a bucket beside a concrete pole.
Photo by EriGle Gon on Unsplash

The reason this matters for hiring timelines is speed. Reconductoring an existing corridor runs about 18 months to three years, against five to 15 years for a new line across new ground, as Howland reported in 2024 on the GridLab and Berkeley study of the approach. Work that starts sooner is work that hires sooner.

There is a catch, and it is a skills catch rather than a steel catch. A 2024 Energy Innovation report on advanced conductor deployment found that the practical barrier was not the product but the practice: crews need the training, the tools and the repetitions to handle a composite core conductor, which does not behave like the aluminum and steel wire they have pulled their whole careers. The same report documents how that gets solved. Manufacturers run hands on training for installers. At one utility, it took a decade of field experience before construction crews came around, and those crews now prefer advanced conductors to the bundled alternative. NV Energy worked through purchasing, spare stock, training and maintenance and got its construction timelines down.

"The experience developed through these grants will be phenomenal."

That is Julia Selker, executive director of the Working for Advanced Transmission Technologies coalition, quoted by St. John. It is a workforce statement. Thirty one projects means a few thousand people learning a technique that a few hundred people in this country have done at scale.

The numbers

The award: $1.9 billion federal, $3.35 billion from the recipients, $5.25 billion total, 31 projects, 26 states, more than 1,500 miles reconductored or rebuilt, close to 21,000 miles fitted with grid enhancing technologies, 23 gigawatts of capacity unlocked, per Utility Dive and Canary Media.

The Pennsylvania piece: up to $71.5 million, 29.3 miles, 230 kilovolts, one utility with 1.5 million customers. Site Selection magazine named PPL Electric a top utility for economic development on September 3, crediting 20 projects it connected in 2025 that represent $12.8 billion in investment and 1,775 new jobs across the state.

The workforce backdrop, from the 2026 U.S. Energy and Employment Report as Maryann Pugh summarized it for MyChesCo on September 8: transmission, distribution and storage employed about 1.5 million people in 2025 and added roughly 28,000 jobs, a 2 percent gain, while electric power transmission and distribution alone added 17,900 workers. Median energy wages ran $63,000 against a national median of $51,000, and construction apprenticeship enrollment climbed 9 percent.

Set that against the hiring math in the report: 67 percent of transmission, distribution and storage employers said hiring was difficult in 2025, and 65 percent of the construction firms inside that sector said the same. Fifteen hundred miles of reconductoring lands on top of that, not instead of it.

Two lineworkers in yellow hard hats work side by side from bucket trucks at the top of a wood pole.
Photo by Roberto Brambilla on Unsplash

What comes next

The grants are selections, not signed awards. PPL says negotiations run over the coming months, and every other recipient is in the same queue. The practical questions from here: which utilities do this work with their own crews and which put it out to contractors, when the conductor orders get placed, and how many apprentices and journeymen each project needs at peak.

The deeper question is where the trained hands come from. Advanced conductor experience sits with a small number of crews, a handful of manufacturers running installer training, and the apprenticeship programs already operating in most of these 26 states. A federal grant can buy wire. It cannot buy repetitions. The companies that get their people trained first will be the ones bidding the next round of this work, and 1,500 miles is only a start on a system with hundreds of thousands of miles of line.

The Bottom Line

Thirty one projects, 26 states, 1,500 miles of wire to pull. The money is federal, the lines belong to the utilities, and the work belongs to crews who will spend the next three years learning a conductor that behaves differently than anything they have hung before. Watch the training schedules. That is where the 1,500 miles actually gets built.

Sources: Ethan Howland, Utility Dive, September 24, 2026 | Jeff St. John, Canary Media, September 24, 2026 | Marin Holt, mgrid, September 24, 2026 | PPL Electric Utilities announcement, September 24, 2026 | U.S. Department of Energy SPARK announcement | Ethan Howland, Utility Dive, April 9, 2024 | Energy Innovation, Supporting Advanced Conductor Deployment, 2024 | Maryann Pugh, MyChesCo, September 8, 2026 | PPL Electric Utilities, Site Selection recognition, September 3, 2026